VT Route 2A, Williston

Written by on October 4, 2018 in VT ROUTE 2A SAFETY IMPROVEMENTS

The following is the anticipated work schedule for the week beginning Monday, October 08, 2018:

Monday:

  • No work due to the Columbus Day holiday.

Tuesday thru Thursday:

  • Complete the installation of new drainage piping across Eastview Circle. Traffic control will be present allowing for one lane of alternating traffic on Eastview during this work.

Tuesday thru Friday:

  • Installation of the flashing beacons for/at the Bittersweet crosswalk.
  • Clean up work within the Morgan Parkway area from the tree cutting.

Motorists should expect minimal delays and use caution while traveling thru the work zone.