The following is the anticipated work schedule for the week beginning Monday, October 08, 2018:
Monday:
- No work due to the Columbus Day holiday.
Tuesday thru Thursday:
- Complete the installation of new drainage piping across Eastview Circle. Traffic control will be present allowing for one lane of alternating traffic on Eastview during this work.
Tuesday thru Friday:
- Installation of the flashing beacons for/at the Bittersweet crosswalk.
- Clean up work within the Morgan Parkway area from the tree cutting.
Motorists should expect minimal delays and use caution while traveling thru the work zone.