The following is the anticipated daytime work schedule for the week beginning Monday, September 23, 2019.
Monday through Friday – 7:00 a.m. to 5:30 p.m.:
- Continue shaping & ditch cleanup after nighttime excavation work
Motorists should have minimal affect by this work. Two-way traffic will be maintained. Pedestrians will be detoured around the work area.
Monday through Thursday – 7:00 p.m. to 6:00 a.m.:
- Continue widening of the east side of Route 2A.
Traffic control will be present allowing for one-lane of alternating traffic within the work area. Motorists should plan for delays.
Please use caution while traveling thru the work zone.