The following is the anticipated daytime work schedule for the week beginning Monday, September 30, 2019.
Monday through Friday – 7:00 a.m. to 5:30 p.m.:
- Continue ditch and shoulder work
- Potential signal work
Motorists should have minimal affect by this work. Two-way traffic will be maintained. Pedestrians will be detoured around the work area.
Monday through Friday – 7:00 p.m. to 6:00 a.m.:
- Continue excavation for the widening of the east side of Route 2A.
Traffic control will be present allowing for one-lane of alternating traffic within the work area. Motorists should plan for delays.
Please use caution while traveling thru the work zone.
Prep for paving Base pavement Paving leveling course