The following is the anticipated daytime work schedule for the week beginning Monday, October 14, 2019.
Monday – No work due to the Columbus Day holiday
Tuesday through Friday – 7:00 a.m. to 5:30 p.m.:
- Continue ditch and shoulder work south of Morgan Parkway
- Continue widening work on James Brown Drive
Tuesday and Wednesday (Wed. if necessary) – 7:00 a.m. to 5:30 p.m.:
- Paving the widened area from Morgan Parkway south to River Cove Road. Traffic control will be present at Morgan Parkway.
Motorists should have minimal affect by this work. Two-way traffic will be maintained. Pedestrians will be detoured around the work area.
Wednesday and Thursday – 7:00 p.m. to 6:00 a.m.:
- Milling (grinding) the existing roadway from the bridge to River Cove Road
Traffic control will be present allowing for one-lane of alternating traffic within the work area. Motorists should plan for delays.
Please use caution while traveling thru the work zone.