VT Route 2A, Williston

Written by on October 11, 2018 in VT ROUTE 2A SAFETY IMPROVEMENTS

The following is the anticipated work schedule for the week beginning Monday, October 15, 2018:

 Monday thru Wednesday 7:00pm to 6:00am:

  • Installation of new drainage piping across VT Route 2A within the Agway/VIP Tire Center area. There will be traffic control present allowing for one lane of alternating traffic during this work.

 Thursday & Friday – Daytime:

  • Complete the installation of new drainage piping across Eastview Circle. Traffic control will be present allowing for one lane of alternating traffic on Eastview during this work.

Monday thru Friday – Daytime:

  • Complete the installation of the flashing beacons for/at the Bittersweet crosswalk.

 

Motorists should expect traffic control to be present allowing for one lane of alternating traffic within the work zone.  Please use caution while traveling thru the work zone.