The following is the anticipated daytime work schedule for the week beginning Saturday, May 16, 2020:
Saturday – 6:00 a.m. to 5:00 p.m.:
- Continue sidewalk construction on the east side between Morgan Parkway and Eastview Circle
- Weather permitting, continue paving the leveling course
Sunday – 4:00 p.m. to 12:00 a.m.:
- Catch basin adjustments throughout the project in anticipation of final paving
Tuesday through Thursday (possibly Friday) – 6:00 p.m. to 6:00 a.m.:
- Weather permitting, final paving of the wearing course
Monday through Friday – 6:00 a.m. to 5:30 p.m.:
- Work at the River Cove Road intersection
- Completion of the sidewalk construction on the east side between Morgan Parkway and Eastview Circle
- Installation of topsoil along the shoulders
Traffic control will be present during all activities allowing for one lane of alternating traffic. Motorists may encounter minor delays.