The following is the anticipated daytime work schedule for the week beginning Tuesday, May 26, 2020:
Monday – No work due to the Memorial Day holiday
Tuesday through Thursday (possibly Friday) – 6:00 p.m. to 6:00 a.m.:
- Weather permitting, pavement markings throughout the project limits
Traffic control will be present allowing for one lane of alternating traffic.
Tuesday through Friday 6:00 a.m. to 5:30 p.m.:
- Sign Installation
- Signal work
- Continue installation of topsoil along the shoulders
Two-way traffic will be maintained.