The following is the anticipated schedule for VT Route 2A & US 2 project:

The following is the anticipated schedule on Route 2 for the week beginning Monday, June 11, 2018:

Monday thru Friday: Daytime – 6:30am to 7:00pm

  • Drainage work between the Harvest Lane/Blair Park and North Brownell Roads intersections in the westbound lane.

 

Motorist be aware that we are going to try to maintain 2-way traffic at all times however use caution while traveling thru the construction areas.

The following is the anticipated schedule on the I-91 Rockingham Bridges:

Written by on June 1, 2018 in Rockingham Bridges-I91

For the week beginning Monday, June 4, 2018:

Monday thru Friday – Daytime:

  • Continued installing beam support hardware on Piers
  • Continue mobilizing cranes to needed locations
  • Continue receiving beams at the lay-down area
  • Continued preparation to begin beam erection to begin Thursday
  • Continued concrete work on Abutment 1 for support walls
  • Complete backfilling at abutment 2 and construct crane pad
  • Truck traffic on Golden Hill Road

Thursday – I-91 ROLLING ROAD BLOCKS  to allow for beam deliveries:

  • 8:00am and 11:00am southbound for approximately 30 minutes
  • 10:00am and 2:00pm northbound for approximately 30 minutes

 Friday – I-91 ROLLING ROAD BLOCKS  to allow for beam deliveries:

  • 8:00am southbound for approximately 30 minutes
  • 10:00am northbound for approximately 30 minutes