For the week beginning Monday, September 3, 2018:
Monday: No work – Happy Labor Day.
Tuesday thru Friday:
- Continued installation of cold mix from No. Williston Road proceeding west to Tiffany Lane.
- Underdrain work continues between Barber Farm Road and the US Route 2 intersection.
MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE WORK ZONE AND DRIVE SLOW!
Commuting motorists should seek alternate routes. Expect delays during peak hours!
The anticipated work schedule for Friday, August 31, 2018 is as follows:
- Continued Installation of cold mix beginning at the Essex/Jericho town line proceeding westbound. Hope to match up with today’s work by 3:00 pm tomorrow and include a painted center line.
- Underdrain work will also continue between Barber Farm Road and the Jericho/Richmond town line – will be off the road with this operation by noon.
- Road maintenance throughout the weekend, as needed.
Traffic control is present allowing for one lane of alternating travel.
USE CAUTION – DRIVE SLOW!
For the week beginning Monday, September 03, 2018:
Monday: No work – Happy Labor Day!
Tuesday thru Friday:
- Prepping side roads and driveway tie-ins from Meehan Road, Bristol proceeding north to the end of the project limits in Starksboro.
Motorists should expect delays as traffic control will be present allowing for one lane of alternating traffic within the construction areas.
- Installation of cold mix beginning at the Essex/Jericho town line proceeding westbound. This didn’t happen today, so we will try for tomorrow – barring any unforeseen circumstances.
- Continued underdrain work will also continue between Barber Farm Road and the Jericho/Richmond town line.
- Installation of cold mix beginning at the Essex/Jericho town line proceeding westbound.
- Continued underdrain work will also continue between Skunk Barber Farm Road and the Jericho/Richmond town line.
The anticipated work schedule is as follows:
- Patching the culvert cuts on both sides of Barber Farm road with pavement (one approx. 500’ west of Barber Farm Road, the other approx. 1500’ east of Barber Farm Road).
- Continued underdrain work will also continue between Skunk Hollow Road and Barber Farm Road.
Traffic control is present allowing for one lane of alternating travel.
USE CAUTION – DRIVE SLOW – NO CENTER LINE!
For the week beginning, Saturday, August 25, 2018:
Saturday:
- 7:00 am Weather permitting, continue 2nd reclaiming phase from Valley View Drive to Tiffany Lane.
Monday thru Friday:
- Complete 2nd reclaiming phase early in the week.
- Installation of cold mix begins from the Essex/Jericho town line proceeding west to Tiffany Lane.
- Underdrain work continues between Skunk Hollow Road and Jericho/Richmond town line.
- Continue slope stabilization work between Barber Farm Road to the intersection of US Route 2.
Traffic control will be present allowing for one lane of alternating traffic within the construction areas.
Motorists please be aware:
- There will not be a center line from the Essex/Jericho Town line to Tiffany Lane
- Rough roadway surface
- Please drive slowly & use caution!
Commuting motorists should seek alternate routes. Expect delays during peak hours!