Archive for August, 2018

The following is the work schedule on VT 117

Written by on August 30, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

For the week beginning Monday, September 3, 2018:

Monday:  No work – Happy Labor Day.

Tuesday thru Friday:

  • Continued installation of cold mix from No. Williston Road proceeding west to Tiffany Lane.
  • Underdrain work continues between Barber Farm Road and the US Route 2 intersection.

 

MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE WORK ZONE AND DRIVE SLOW!

Commuting motorists should seek alternate routes.  Expect delays during peak hours!

VT 117 – August 31, 2018

Written by on August 30, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The anticipated work schedule for Friday, August 31, 2018 is as follows:

  • Continued Installation of cold mix beginning at the Essex/Jericho town line proceeding westbound. Hope to match up with today’s work by 3:00 pm tomorrow and include a painted center line.
  • Underdrain work will also continue between Barber Farm Road and the Jericho/Richmond town line – will be off the road with this operation by noon.
  • Road maintenance throughout the weekend, as needed.

Traffic control is present allowing for one lane of alternating travel.

USE CAUTION – DRIVE SLOW!

The anticipated schedule for the I-91 Rockingham Bridges

Written by on August 30, 2018 in Rockingham Bridges-I91

For the week beginning Monday, September 03, 2018:

Monday:  No work – Happy Labor Day!

Tuesday thru Thursday – 5:00pm to 5:00am
Tuesday thru Friday – Daytime:

  • Continue installation of overhang.
  • Continue installing the steel decking
  • Continue removal of temporary supports that held the beams.

The anticipated schedule for VT 116

Written by on August 30, 2018 in Middlebury-Starksboro VT 116

For the week beginning Monday, September 03, 2018:

Monday:  No work – Happy Labor Day!

Tuesday thru Friday:

  • Prepping side roads and driveway tie-ins from Meehan Road, Bristol proceeding north to the end of the project limits in Starksboro.

Motorists should expect delays as traffic control will be present allowing for one lane of alternating traffic within the construction areas.

The following is the anticipated schedule for Bridge #8:

Written by on August 30, 2018 in BRIDGE 8 VT ROUTE 17

For the week beginning Monday, September 03, 2018:

Monday thru Friday:

  • Continued removal of old concrete pier
  • Continue removal of causeway
  • General cleanup work throughout

 Motorists should expect minimal delays!

VT 2A – Week beginning September 4, 2018

Written by on August 30, 2018 in VT ROUTE 2A SAFETY IMPROVEMENTS

The anticipated work schedule for this week is as follows:

  • Installation of construction signage throughout the project limits.

Motorists should expect minimal delays this week.

 

VT 117 – August 30, 2018

Written by on August 29, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
The anticipated work schedule is as follows:
  • Installation of cold mix beginning at the Essex/Jericho town line proceeding westbound. This didn’t happen today, so we will try for tomorrow – barring any unforeseen circumstances.
  • Continued underdrain work will also continue between Barber Farm Road and the Jericho/Richmond town line.
 
Traffic control is present allowing for one lane of alternating travel.
 
USE CAUTION – DRIVE SLOW – NO CENTER LINE!

VT 117 – August 29, 2018

Written by on August 28, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
The anticipated work schedule is as follows:
 
  • Installation of cold mix beginning at the Essex/Jericho town line proceeding westbound.
  • Continued underdrain work will also continue between Skunk Barber Farm Road and the Jericho/Richmond town line.
Traffic control is present allowing for one lane of alternating travel.
 
USE CAUTION – DRIVE SLOW – NO CENTER LINE!

VT 117 – August 28, 2018

Written by on August 27, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The anticipated work schedule is as follows:

  • Patching the culvert cuts on both sides of Barber Farm road with pavement (one approx. 500’ west of Barber Farm Road, the other approx. 1500’ east of Barber Farm Road).
  • Continued underdrain work will also continue between Skunk Hollow Road and Barber Farm Road.

Traffic control is present allowing for one lane of alternating travel.

USE CAUTION – DRIVE SLOW – NO CENTER LINE!

The anticipated schedule on VT 117:

Written by on August 23, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

For the week beginning, Saturday, August 25, 2018:

Saturday:

  • 7:00 am Weather permitting, continue 2nd reclaiming phase from Valley View Drive to Tiffany Lane.

Monday thru Friday:

  • Complete 2nd reclaiming phase early in the week.
  • Installation of cold mix begins from the Essex/Jericho town line proceeding west to Tiffany Lane.
  • Underdrain work continues between Skunk Hollow Road and Jericho/Richmond town line.
  • Continue slope stabilization work between Barber Farm Road to the intersection of US Route 2.

Traffic control will be present allowing for one lane of alternating traffic within the construction areas.

Motorists please be aware:

  • There will not be a center line from the Essex/Jericho Town line to Tiffany Lane
  • Rough roadway surface
  • Please drive slowly & use caution!

Commuting motorists should seek alternate routes.  Expect delays during peak hours!

 