VT 117 – November 01, 2018

Written by on October 31, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
The anticipated work schedule is as follows:
  • Shoulder work to continue between VT 289 and Tiffany Lane.
  • Curb work to continue at Sand Hill Road.
  • Culvert work to continue between Skunk Hollow Road and Barber Farm Road.
  • Signal work at the VT 289 off ramp.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.  Motorists expect delays!
 
DRIVE SLOW – USE CAUTION!

VT 117 – October 31, 2018

Written by on October 30, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
The anticipated work schedule is as follows:
  • Shoulder work to continue between VT 289 and Tiffany Lane.
  • Curb work to continue at Sand Hill Road.
  • Culvert work to continue between Skunk Hollow Road and Barber Farm Road.
  • Signal work at the VT 289 off ramp.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.  Motorists expect delays!
 
DRIVE SLOW – USE CAUTION!

VT 117 – October 30, 2018

Written by on October 29, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
The anticipated work schedule is as follows:
  • Shoulder work to continue between VT 289 and Tiffany Lane.
  • Curb work to continue at Sand Hill Road.
  • Culvert work to continue between Barber Farm Road and the Jericho/Richmond town line.
  • Signal work at the VT 289 off ramp.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.  Motorists expect delays!
 
DRIVE SLOW – USE CAUTION!

Rockingham Bridges I-91

Written by on October 25, 2018 in Rockingham Bridges-I91
Rockingham Bridges I-91

The following is the anticipated work schedule for the week beginning Monday, October 29, 2018:

I-91 northbound bridge activities:

Monday thru Thursday – 5:00pm to 5:00am
Monday thru Friday – Daytime:

  • Continue work on both approaches.
  • Continue curing of the concrete deck placements.
  • Continue placement of the barrier curb.

Please use caution while traveling thru the work zone.

Curing Concrete

Curing Concrete

The anticipated work schedule on VT 117

Written by on October 25, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

For the week beginning Monday, October 29, 2018 – Please note at this time of the year work can be weather dependent.

 Monday & Tuesday:

  • Completion of shoulder / ditch work between the VT-289 intersection and Tiffany Lane
  • Completion of curb and structure rehabilitation work at the Sand Hill Road intersection.

Monday thru Friday:

  • Abutting side road prep work to beginning at the west end of the project in Essex proceeding east.

Wednesday thru Friday:

  • Culvert work to resume between Barber Farm Road and the Jericho/Richmond town line.

 

COMMUTING MOTORISTS SHOULD SEEK ALTERNATE ROUTES.  EXPECT DELAYS DURING PEAK HOURS!

MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE WORK ZONE AND DRIVE SLOW!

VT 117 – October 26, 2018

Written by on October 25, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
The anticipated work schedule is as follows:
  • Structure, shoulder, sidewalk and patching pothole work to continue between Sand Hill Road and Tiffany Lane.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.  Motorists expect delays!
 
DRIVE SLOW – USE CAUTION!

VT Route 2A – Williston

Written by on October 25, 2018 in VT ROUTE 2A SAFETY IMPROVEMENTS

This project is complete for the 2018 construction season.  I will be back in touch in the Spring 2019!

 May you have a safe holiday season and winter.

 

Anyone with questions or concerns regarding this project may contact Stephanie Barrett, Public Outreach Coordinator at 802-862-6085.

The anticipated work schedule on VT 116:

Written by on October 25, 2018 in Middlebury-Starksboro VT 116

The work schedule for the week beginning Saturday, October 27, 2018:

Saturday thru Friday:

  • Weather permitting, continue paving from Cobble Road, Bristol to the Bristol Village line.
  • Weather permitting, paving abutting side roads & driveway aprons beginning in East Middlebury and proceeding north.

Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.

VT 117 – October 25, 2018

Written by on October 24, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
The anticipated work schedule is as follows:
  • Shoulder, sidewalk and patching pothole work to continue between Sand Hill Road and Tiffany Lane.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.  Motorists expect delays!
 
DRIVE SLOW – USE CAUTION!

VT 117 – October 24, 2018

Written by on October 23, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
The anticipated work schedule is as follows:
  • Structure rehabilitation and sidewalk work to continue between VT 289 ramps and Tiffany Lane.
  • Shoulder / ditch work will continue between Sand Hill Road and Tiffany Lane.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.  Motorists expect delays!
 
DRIVE SLOW – USE CAUTION!