- Weather permitting, paving between/around the VT 289 on/off ramps with leveling course.
- Weather permitting, continued paving base course between Valleyview Road and Tiffany Lane.
- Continued culvert work Barber Farm Road and Jericho/Richmond town line.
The following is the anticipated work schedule for the week beginning Monday, October 15, 2018:
I-91 northbound bridge activities:
Monday thru Thursday – 5:00pm to
Monday thru Friday – Daytime:
- Continue placing concrete deck segments.
- Complete installation deck reinforcing.
- Complete approach road work up to the approach slab area.
- Begin forming the approach slabs.
- Begin installation of reinforcement for the barrier curb.
Please drive slow and use caution while traveling thru the work zone.
The work schedule for the week beginning Monday, October 15, 2018:
Monday thru Saturday:
- Weather permitting, paving from East Middlebury to Bristol.
Wednesday thru Saturday:
- Weather permitting, paving abutting driveway tie-ins beginning in East Middlebury and proceeding north to Bristol.
Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.
The following is the anticipated work schedule for the week beginning Monday, October 15, 2018:
Monday thru Wednesday 7:00pm to 6:00am:
- Installation of new drainage piping across VT Route 2A within the Agway/VIP Tire Center area. There will be traffic control present allowing for one lane of alternating traffic during this work.
Thursday & Friday – Daytime:
- Complete the installation of new drainage piping across Eastview Circle. Traffic control will be present allowing for one lane of alternating traffic on Eastview during this work.
Monday thru Friday – Daytime:
- Complete the installation of the flashing beacons for/at the Bittersweet crosswalk.
Motorists should expect traffic control to be present allowing for one lane of alternating traffic within the work zone. Please use caution while traveling thru the work zone.
- Patching of the culvert crossing near the Jericho/Richmond town line.
- Shoulder / ditch work will continue between VT 289 and Greenfield Road.
- Continued culvert work Barber Farm Road and Bradley Bow Road.
- Guardrail work will continue around the Sand Hill Road intersection.
- General clean up work between Valley View Road and Tiffany Lane.
- Weather permitting, paving to resume between Valley View Drive and Tiffany Lane.
- Shoulder / ditch work will continue between N. Williston Road and Sand Hill Road.
- Continued culvert work Barber Farm Road and Bradley Bow Road.
- Guardrail work will continue between N. Williston Road and Sand Hill Road.
The following is the anticipated work schedule for the week beginning Monday, October 08, 2018.
I-91 northbound bridge activities:
Monday thru Thursday – 5:00pm to 5:00am
Monday thru Friday – Daytime:
- Begin construction on the northbound abutment approach.
- Begin placing concrete deck segments.
- Continue installation deck reinforcing.
- Complete forming back wall at the southern abutment.
Please drive slow and use caution while traveling thru the construction zone.
The following is the anticipated work schedule for the week beginning Monday, October 08, 2018:
Monday:
- No work due to the Columbus Day holiday.
Tuesday thru Thursday:
- Complete the installation of new drainage piping across Eastview Circle. Traffic control will be present allowing for one lane of alternating traffic on Eastview during this work.
Tuesday thru Friday:
- Installation of the flashing beacons for/at the Bittersweet crosswalk.
- Clean up work within the Morgan Parkway area from the tree cutting.
Motorists should expect minimal delays and use caution while traveling thru the work zone.
The following is the anticipated work schedule for the week beginning Monday, October 8, 2018:
Monday:
- No work due to the Columbus Day holiday.
Tuesday thru Friday:
- Culvert work continues between Barber Farm Road and the Jericho/Richmond town line.
- Structure rehabilitation work continues between the VT-289 intersection to Tiffany Lane.
- Shoulder/ditch work continues from Greenfield Road to Tiffany Lane.
- Continued guardrail work between N. Williston Road and Tiffany Lane.
Wednesday thru Friday:
- Weather permitting, paving resumes from VT-289 to Tiffany Lane.
COMMUTING MOTORISTS SHOULD SEEK ALTERNATE ROUTES. EXPECT DELAYS DURING PEAK HOURS!
MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE WORK ZONE AND DRIVE SLOW!
For the week beginning Monday, October 08, 2018:
Monday:
- No work due to the Columbus Day holiday.
Tuesday thru Saturday:
- Weather permitting, final paving to begin south of Bristol Village to East Middlebury.
Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.