Archive for October, 2018

VT 117 – October 12, 2018

Written by on October 11, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
The anticipated work schedule is as follows:
  • Weather permitting, paving between/around the VT 289 on/off ramps with leveling course.
  • Weather permitting, continued paving base course between Valleyview Road and Tiffany Lane.
  • Continued culvert work Barber Farm Road and Jericho/Richmond town line.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.  Motorists expect delays!
 
DRIVE SLOW – USE CAUTION!

Rockingham Bridges I-91

Written by on October 11, 2018 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Monday, October 15, 2018:

I-91 northbound bridge activities:        

Monday thru Thursday – 5:00pm to
Monday thru Friday – Daytime:

  • Continue placing concrete deck segments.
  • Complete installation deck reinforcing.
  • Complete approach road work up to the approach slab area.
  • Begin forming the approach slabs.
  • Begin installation of reinforcement for the barrier curb.

Please drive slow and use caution while traveling thru the work zone.

The anticipated work schedule on VT 116:

Written by on October 11, 2018 in Middlebury-Starksboro VT 116

The work schedule for the week beginning Monday, October 15, 2018:

Monday thru Saturday:

  • Weather permitting, paving from East Middlebury to Bristol.

Wednesday thru Saturday:

  • Weather permitting, paving abutting driveway tie-ins beginning in East Middlebury and proceeding north to Bristol.

Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.

VT Route 2A, Williston

Written by on October 11, 2018 in VT ROUTE 2A SAFETY IMPROVEMENTS

The following is the anticipated work schedule for the week beginning Monday, October 15, 2018:

 Monday thru Wednesday 7:00pm to 6:00am:

  • Installation of new drainage piping across VT Route 2A within the Agway/VIP Tire Center area. There will be traffic control present allowing for one lane of alternating traffic during this work.

 Thursday & Friday – Daytime:

  • Complete the installation of new drainage piping across Eastview Circle. Traffic control will be present allowing for one lane of alternating traffic on Eastview during this work.

Monday thru Friday – Daytime:

  • Complete the installation of the flashing beacons for/at the Bittersweet crosswalk.

 

Motorists should expect traffic control to be present allowing for one lane of alternating traffic within the work zone.  Please use caution while traveling thru the work zone.

VT117 – October 11, 2018

Written by on October 10, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
The anticipated work schedule is as follows:
  • Patching of the culvert crossing near the Jericho/Richmond town line.
  • Shoulder / ditch work will continue between VT 289 and Greenfield Road.
  • Continued culvert work Barber Farm Road and Bradley Bow Road.
  • Guardrail work will continue around the Sand Hill Road intersection.
  • General clean up work between Valley View Road and Tiffany Lane.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.  Motorists expect delays!
 
DRIVE SLOW – USE CAUTION!

VT 117 – October 10, 2018

Written by on October 9, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
The anticipated work schedule is as follows:
  • Weather permitting, paving to resume between Valley View Drive and Tiffany Lane.
  • Shoulder / ditch work will continue between N. Williston Road and Sand Hill Road.
  • Continued culvert work Barber Farm Road and Bradley Bow Road.
  • Guardrail work will continue between N. Williston Road and Sand Hill Road.
Traffic control will be present allowing for one lane of alternating traffic through the work zones.  Motorists expect delays!
 
DRIVE SLOW – USE CAUTION!

Rockingham Bridges I-91

Written by on October 4, 2018 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Monday, October 08, 2018.

 I-91 northbound bridge activities:

Monday thru Thursday – 5:00pm to 5:00am
Monday thru Friday – Daytime:

  • Begin construction on the northbound abutment approach.
  • Begin placing concrete deck segments.
  • Continue installation deck reinforcing.
  • Complete forming back wall at the southern abutment.

Please drive slow and use caution while traveling thru the construction zone.

VT Route 2A, Williston

Written by on October 4, 2018 in VT ROUTE 2A SAFETY IMPROVEMENTS

The following is the anticipated work schedule for the week beginning Monday, October 08, 2018:

Monday:

  • No work due to the Columbus Day holiday.

Tuesday thru Thursday:

  • Complete the installation of new drainage piping across Eastview Circle. Traffic control will be present allowing for one lane of alternating traffic on Eastview during this work.

Tuesday thru Friday:

  • Installation of the flashing beacons for/at the Bittersweet crosswalk.
  • Clean up work within the Morgan Parkway area from the tree cutting.

Motorists should expect minimal delays and use caution while traveling thru the work zone.

Anticipated schedule on VT 117

Written by on October 4, 2018 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The following is the anticipated work schedule for the week beginning Monday, October 8, 2018:

 Monday:

  • No work due to the Columbus Day holiday.

 Tuesday thru Friday:

  • Culvert work continues between Barber Farm Road and the Jericho/Richmond town line.
  • Structure rehabilitation work continues between the VT-289 intersection to Tiffany Lane.
  • Shoulder/ditch work continues from Greenfield Road to Tiffany Lane.
  • Continued guardrail work between N. Williston Road and Tiffany Lane.

 Wednesday thru Friday:

  • Weather permitting, paving resumes from VT-289 to Tiffany Lane.

COMMUTING MOTORISTS SHOULD SEEK ALTERNATE ROUTES.  EXPECT DELAYS DURING PEAK HOURS!

MOTORISTS PLEASE USE CAUTION WHILE TRAVELING THRU THE WORK ZONE AND DRIVE SLOW!

The anticipated work schedule for VT Route 116

Written by on October 4, 2018 in Middlebury-Starksboro VT 116

For the week beginning Monday, October 08, 2018:

Monday:

  • No work due to the Columbus Day holiday.

Tuesday thru Saturday:

  • Weather permitting, final paving to begin south of Bristol Village to East Middlebury.

Motorists should expect delays with traffic control present allowing for one lane of alternating traffic within the construction areas.

Top