Archive for April, 2019
Monday thru Friday:
- Reclaiming of the roadway surface between Skunk Hollow Road and the VT Route 117/US Route 2 intersection.
- Roadway excavation to begin at the Essex/Jericho town line proceeding east throughout the week.
- Signal work at the intersection of VT 289 and VT Route 117.
Monday thru Wednesday:
- Continued Guardrail work throughout the project limits.
Motorist should expect delays!
Traffic control will be present allowing for one-lane of alternating travel within the construction zones.
The following is the anticipated work schedule on the I-91 bridges for the week beginning Monday, April 29, 2019:
Monday thru Friday:
- Work begins on building the crossover to re-route all traffic onto the NB Bridge
- Work continues on SB Pier #3 to include placement of 2nd shaft
- Prep work for 1st placement of concrete at SB Pier #2
NARROW LANES – USE CAUTION!
Tomorrow, April 26, 2019 @ 6:30a.m.:
- Weather permitting, there will be a I-91 northbound rolling road block for line striping before northbound motorists will be directed onto one lane of the newly constructed bridge. Motorists can anticipate approximately a 25-minute delay in their travels. Southbound traffic will still travel over one lane of the existing southbound bridge until a crossover is built.
- I-91 Exit 6 northbound On-Ramp will be opened up within an hour after the rolling road block clears and traffic is back up to speed over to the new I-91 Northbound Bridge.
Please note: If weather does not permit this to happen then the rain date will be for Monday, April 29, 2019 @ 9:30a.m.
The following is an update to the work schedule for the week beginning April 29, 2019:
Monday:
- Weather permitting, paving in Bristol at the VT-116/VT-17/Burpee Road intersection along with the surrounding area of Airport Road in preparation of final paving.
Tuesday thru Friday:
- Installation of center line rumble strip throughout the project limits.
- General cleanup work throughout the project limits.
Motorists should expect delays with traffic control present allowing for 1-lane of alternating traffic within the construction zone.