Archive for May, 2019
Monday thru Friday:
- Continue reclaiming to stabilize the roadway base from the Jericho/Richmond town line proceeding west
- Continue roadway maintenance
Motorist should expect delays!
MOTORISTS PLEASE SLOW DOWN! SAFETY FIRST!
Traffic control will be present allowing for one-lane of alternating travel within the construction zones.
Below is the anticipated work schedule for the week beginning Monday, June 03, 2019:
Monday thru Friday:
- Preparation work for demolition of SB Pier #1.
- Work continues on SB Piers #2 & #3.
- Begin removal of the existing southbound bridge deck
- Installation of the southbound traffic control devises.
TUESDAY:
- 9:30am there will be a rolling roadblock for southbound motorists in preparation of opening the southbound crossover. Motorists can anticipate approximately a 20-minute delay in their travels. If time does not allow for all work to be completed within the 20 minutes, there will be another rolling roadblock at 11:00am for approximately another 20-minute delay.
TUESDAY THRU THURSDAY:
- EXIT 6 SOUTHBOUND OFF-RAMP WILL BE CLOSED AT 9:30am June 4, 2019 until the end of the workday June 6, 2019. Motorists will be detoured using Exit 7 Off-Ramp then follow the signed detour on Route 5 southbound. All trucks over 14’ high will follow a signed detoured using Route 11.
KEEP YOUR HEADS UP AND YOUR CELL PHONE DOWN!
We ask motorists to be patient and understanding as we get the roadway stabilized within this intersection today and tomorrow. This work includes large equipment and there is a lot of traffic. We understand you are experiencing long delays however we are doing our best to shorten everyone’s delays. Thank you for patience!
MOTORISTS PLEASE SLOW DOWN!
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED!
Monday:
- No work due to the Memorial Day holiday
Tuesday thru Friday:
- The second reclaiming process to begin to stabilize the roadway base between Skunk Hollow Road and the US Route 2/VT 117 intersection
- General cleanup work and roadway maintenance
Motorist should expect delays!
MOTORISTS PLEASE SLOW DOWN! SAFETY FIRST!
Traffic control will be present allowing for one-lane of alternating travel within the construction zones.
- Continue roadway excavation, shaping and drainage work between the Essex/Jericho town line and the intersection of US Route 2/VT 117
- General cleanup work and roadway maintenance
Motorist should expect delays!
MOTORISTS PLEASE SLOW DOWN! SAFETY FIRST!
Traffic control will be present allowing for one-lane of alternating travel within the construction zones.
Below is the anticipated work schedule for the week beginning Monday, May 27, 2019:
Monday:
No work due to the Memorial Day Holiday!
Tuesday thru Friday:
- Work continues on the installation of the southbound crossover to include paving, shoulders & line striping.
- Work continues on SB Piers #2 & #3.
- Prep work on the existing southbound bridge for start of demolition
- Installation of the southbound traffic control devises.
REMINDERS:
- JUNE 04, 2019 at 9:30am there will be a rolling roadblock for southbound motorists in preparation of opening the southbound crossover. Motorists can anticipate approximately a 20-minute delay in their travels. If time does not allow for all work to be completed within the 20 minutes, there will be another rolling roadblock at 11:00am for approximately another 20-minute delay.
- JUNE 4, 2019 THRU JUNE 6, 2019 the EXIT 6 SOUTHBOUND OFF-RAMP WILL BE CLOSED AT 9:30am June 4, 2019 until the end of the workday June 6, 2019. Motorists will be detoured using Exit 7 Off-Ramp then follow the signed detour on Route 5 southbound. All trucks over 14’ high will follow a signed detoured using Route 11.