The anticipated work schedule for the week beginning July 01, 2019

Monday through Wednesday @ noon:

  • Weather permitting, continue paving.

MOTORISTS SHOULD EXPECT DELAYS!

Traffic control will be present allowing for one lane of alternating traffic.

Work will resume on Monday, July 8, 2019 after the Independence Day holiday.

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED!

The anticipated work schedule on VT 117 for June 28 & 29, 2019

Friday beginning mid-morning approx. 9:30 a.m. and Saturday beginning at approx. 7:00 a.m.:

• Weather permitting, continue paving from Rogers Lane to Bradley Bow Road.

Motorists can expect long delays.

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED!

Rockingham Bridges I-91

Written by on June 27, 2019 in Rockingham Bridges-I91

Below is the anticipated work schedule for the week beginning Monday, July 01, 2019:

Monday 7 a.m. until Wednesday @ noon (24-hour days) :

  • Continue removal of bridge rail and curb

KEEP YOUR HEAD UP AND YOUR CELL PHONE DOWN!

The anticipated work schedule on VT 116

Written by on June 27, 2019 in Middlebury-Starksboro VT 116

The following is an update to the work schedule for the week beginning July 01, 2019:

Monday thru Friday:

  • There is no work scheduled for this week.

The anticipated work schedule on VT 117 for June 27, 2019

The anticipated work schedule on VT 117 for June 27, 2019

Beginning mid-morning approx. 9 am – 10 am start:

• Weather permitting, continue paving from the intersection of Route 2 in Richmond proceeding west.

Motorists can expect long delays.

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED!

The anticipated work schedule on VT 117 for June 26, 2019

Beginning mid-morning approx. 9 am – 10 am start:

• Weather permitting, paving to begin from the intersection of Route 2 in Richmond proceeding west.

Motorists can expect long delays.

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED!

The anticipated work schedule on VT 117 for June 25, 2019

  • Continue guardrail installation between the Skunk Hollow Road and Barber Farm Road

Motorists can expect delays.

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED!

The anticipated work schedule on VT 117 for the week beginning June 24, 2019

Monday – Friday:

  • Continue guardrail installation between Skunk Hollow Road and Barber Farm Road

Wednesday – Saturday:

  • Weather permitting, paving to begin at the intersection of US Route 2 and proceeding west on VT Route 117. M

MOTORISTS SHOULD EXPECT EXTENDED DELAYS!

Traffic control will be present allowing for one lane of alternating traffic.

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED!

The anticipated work schedule on VT 116

Written by on June 20, 2019 in Middlebury-Starksboro VT 116

The following is an update to the work schedule for the week beginning June 24, 2019:

Monday thru Friday:

  • Weather permitting, new pavement markings throughout the project limits
  • Various miscellaneous punch-list items throughout the project limits

Motorists should expect minor delays!

Rockingham Bridges I-91

Written by on June 20, 2019 in Rockingham Bridges-I91
Rockingham Bridges I-91

Below is the anticipated work schedule for the week beginning Monday, June 24, 2019:

Monday 7 a.m. to Friday @ noon (24-hour days) :

  • Continue removal of bridge rail and curb
  • Relocate crane to trestle

KEEP YOUR HEADS UP AND YOUR CELL PHONE DOWN!