- Weather permitting, continue installation of cold mix from Barber Farm Road to the Essex/Jericho town line.
- Line striping throughout the project limits
- Tentative signal installation at the VT-289 intersection
MOTORISTS SHOULD EXPECT DELAYS!
Traffic control will be present allowing for one lane of alternating traffic.
MOTORISTS PLEASE SLOW DOWN!
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED!
Below is the anticipated work schedule for the week beginning Monday, June 17, 2019:
Monday thru Friday:
- Continue removal of bridge rail and curb
- Continue removal of the existing southbound bridge deck
- Work continues on SB Piers #2 & #3.
NOTE: New summer hours begins this week with double shifts as follows:
- Monday: 7am to 6pm
- Tuesday thru Thursday: 6am to 6pm
- Friday: 6am to noon
- Monday thru Thursday: 6pm to 6am