ALL WORK THIS WEEK IS EXPECTED TO BE THROUGHOUT THE PROJECT LIMITS.
Monday and Tuesday:
- Continue milling the approaches on each end of the project along with all side road approaches
Wednesday through Friday:
- Driveway paving preparation work
Monday through Friday:
- Shoulder clean up and ditch work
Traffic control will be present allowing for one-lane of alternating travel within the construction zones. The speed limit will be enforced!
MOTORISTS, PLEASE SLOW DOWN! SAFETY FIRST!
The following is the anticipated work schedule for the week beginning Monday, August 12, 2019:
Wednesday thru Friday – Daytime:
- Underground directional drilling at the intersection of James Brown Drive and VT Route 2A in anticipation of installing the traffic signal.
Motorists should not affected by this work. Pedestrians will be accommodated.
Please use caution while traveling thru the work zone.
Below is the anticipated work schedule for the week beginning Monday, August 12, 2019:
Southbound I-91 bridge activities:
Monday through Friday:
- Continue substructure removal
- Continue Pier 3 shaft section 4
- Continue Pier 2 shaft section 3
- Work continues on each abutment approaches
- Demolition of the existing southbound Pier 1
- Continue maintenance of traffic control devises.
KEEP YOUR HEAD UP AND YOUR CELL PHONE DOWN!
Monday through Friday:
- Driveway paving preparation work
- Shoulder clean up and ditch work
Wednesday and Thursday:
- Milling the approaches on each end of the project along with all side road approaches
Traffic control will be present allowing for one-lane of alternating travel within the construction zones. The speed limit will be enforced!
MOTORISTS, PLEASE SLOW DOWN! SAFETY FIRST!