Archive for August, 2019
Monday and Tuesday 7:00 a.m. to 6:00 p.m.
- Continue shoulder clean up and ditch work throughout the project limits
Thursday and Friday 7:30 a.m. to 6:30 p.m.:
- Installation of a new traffic signal mast arm at the VT-289 intersection. Motorists can expect a northbound off-ramp lane closure and delays.
MOTORISTS PLEASE SLOW DOWN!
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED!
The following is the anticipated work schedule for the week beginning Monday, August 19, 2019:
Wednesday thru Friday – Daytime:
- Continue work off the roadway within the James Brown Drive intersection.
Motorists should have minimal to no affect by this work. Pedestrians will be accommodated.
Please use caution while traveling thru the work zone.
Below is the anticipated work schedule for the week beginning Monday, August 19, 2019:
Southbound I-91 bridge activities:
Monday through Friday:
- Continue Pier 3 shaft section 4
- Continue Pier 2 shaft section 3
- Work continues on each abutment approaches
- Demolition of the existing southbound Pier 1
- Begin work on building the new Pier 1
- Continue maintenance of traffic control devises.
KEEP YOUR HEAD UP AND YOUR CELL PHONE DOWN!