Archive for September, 2019

VT Route 2A – Williston

Written by on September 26, 2019 in VT ROUTE 2A SAFETY IMPROVEMENTS

The following is the anticipated daytime work schedule for the week beginning Monday, September 30, 2019.  

Monday through Friday – 7:00 a.m. to 5:30 p.m.:

  • Continue ditch and shoulder work
  • Potential signal work

Motorists should have minimal affect by this work.  Two-way traffic will be maintained.  Pedestrians will be detoured around the work area.

Monday through Friday – 7:00 p.m. to 6:00 a.m.:

  • Continue excavation for the widening of the east side of Route 2A.

Traffic control will be present allowing for one-lane of alternating traffic within the work area. Motorists should plan for delays.

   Please use caution while traveling thru the work zone.

The anticipated work schedule on VT 117 for the week beginning September 30, 2019

Written by on September 26, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

Monday thru Friday:

  • Weather permitting, continue paving abutting side roads and driveway tie-ins.
  • Continue shoulder work throughout the project limits
  • Weather permitting, pavement markings throughout the project limits
  • Continue sign installation
  • General cleanup work throughout the project limits

MOTORISTS SHOULD PLAN FOR DELAYS

Traffic control will be present allowing for one-lane of alternating travel within the construction zones.  The speed limit will be enforced!

Rockingham Bridges I-91

Written by on September 26, 2019 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Saturday, September 28, 2019

Southbound I-91 bridge activities:

Saturday, Monday through Friday:

  • Continue work on Pier 2 for cap placement
  • Form work for placing shaft 1 at Pier 1
  • Work continues at the northbound abutment (#2) approach
  • Work continues on the southbound abutment (#1) approach
  • Complete demolition of the old southbound Piers
  • Continue maintenance of traffic control devises.

The anticipated work schedule on VT 117 for September 27, 2019

Written by on September 26, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • Weather permitting, continue hand paving abutting driveway tie-ins in Essex proceeding east.
  • Continue sign installation

MOTORISTS EXPECT DELAYS!

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED – FINES ARE DOUBLED!

The anticipated work schedule on VT 117 for September 26, 2019

Written by on September 25, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • Weather permitting, continue hand paving abutting driveway tie-ins in Essex proceeding east.
  • Continue sign installation
  • Continue signal work at the VT-289 intersection

MOTORISTS EXPECT DELAYS!

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED – FINES ARE DOUBLED!

The anticipated work schedule on VT 117 for September 25, 2019

Written by on September 24, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • Weather permitting, continue hand paving abutting driveway tie-ins in Essex proceeding east.
  • Continue sign installation
  • Continue signal work at the VT-289 intersection

MOTORISTS EXPECT DELAYS!

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED – FINES ARE DOUBLED!

The anticipated work schedule on VT 117 for September 24, 2019

Written by on September 23, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • Weather permitting, continue hand paving abutting driveway tie-ins in Essex proceeding east.
  • Continue sign installation
  • Continue signal work at the VT-289 intersection

MOTORISTS EXPECT DELAYS!

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED – FINES ARE DOUBLED!

The anticipated work schedule on VT 117 for September 21, 2019

Written by on September 20, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • Continue sign installation

MOTORISTS EXPECT MINOR DELAYS

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED – FINES ARE DOUBLED!

The anticpated work schedule on VT 117 for the week beginning September 21, 2019

Written by on September 19, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
The anticpated work schedule on VT 117 for the week beginning September 21, 2019

Saturday:

  • Continue sign installation

Monday through Wednesday:

  • Weather permitting, continue hand paving abutting driveway tie-ins in Essex proceeding east.

Monday & Tuesday:

  • Continue signal work at the VT-289/117 intersection

Tuesday and Thursday:

  • Weather permitting, continue paving abutting side roads and large driveway tie-ins.

MOTORISTS SHOULD PLAN FOR DELAYS

Traffic control will be present allowing for one-lane of alternating travel within the construction zones.  The speed limit will be enforced!

The anticipated work schedule on VT 117 for September 20, 2019

Written by on September 19, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • Continue sign installation
  • Installation of pavement markings on VT 117 mainline.

MOTORISTS EXPECT DELAYS!

MOTORISTS PLEASE SLOW DOWN! 
SAFETY FIRST!
SPEED LIMIT WILL BE ENFORCED – FINES ARE DOUBLED!

Top