Archive for October, 2019

DUE TO THE WEATHER FORECAST THERE WILL NOT BE ANY WORK OCTOBER 17, 2019 ON VT 117

Written by on October 16, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

The anticipated work schedule on VT 117 for October 16, 2019

Written by on October 15, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • Weather permitting, continue pavement markings
  • Continue sign installation
  • General cleanup work

PLEASE SLOW DOWN!  SAFETY FIRST!

The anticipated work schedule on VT 117 for the week beginning October 14, 2019

Written by on October 10, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

Monday – No work due to the Columbus Day holiday

Tuesday through Friday:

  • Weather permitting, continue pavement markings from Sand Hill Road to Route 2.
  • Continue mailbox adjustments
  • Project cleanup work

MOTORISTS SHOULD EXPECT MINIMAL DELAYS!

Traffic control will be present allowing for one-lane of alternating travel within the construction zones.  The speed limit will be enforced!

PLEASE SLOW DOWN!  SAFETY FIRST!

The anticipated work schedule for October 11, 2019 until noon

Written by on October 10, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • Continue pavement markings

MOTORISTS CAN EXPECT MINIMAL DELAYS!

VT Route 2A – Williston

Written by on October 10, 2019 in VT ROUTE 2A SAFETY IMPROVEMENTS

The following is the anticipated daytime work schedule for the week beginning Monday, October 14, 2019.  

Monday – No work due to the Columbus Day holiday

Tuesday through Friday – 7:00 a.m. to 5:30 p.m.:

  • Continue ditch and shoulder work south of Morgan Parkway
  • Continue widening work on James Brown Drive

Tuesday and Wednesday (Wed. if necessary) – 7:00 a.m. to 5:30 p.m.:

  • Paving the widened area from Morgan Parkway south to River Cove Road. Traffic control will be present at Morgan Parkway.

Motorists should have minimal affect by this work.  Two-way traffic will be maintained.  Pedestrians will be detoured around the work area.

Wednesday and Thursday – 7:00 p.m. to 6:00 a.m.:

  • Milling (grinding) the existing roadway from the bridge to River Cove Road

Traffic control will be present allowing for one-lane of alternating traffic within the work area. Motorists should plan for delays.

   Please use caution while traveling thru the work zone.

Rockingham Bridges I-91

Written by on October 10, 2019 in Rockingham Bridges-I91

The following is the anticipated work schedule for the week beginning Tuesday, October 15, 2019

Southbound I-91 bridge activities:

Tuesday through Friday:

  • Continue work on Pier 2
  • Form work for placing shaft 2 at Pier 1
  • Breakdown of old Pier 1
  • Work continues at the northbound abutment (#2) approach
  • Work continues on the southbound abutment (#1) approach
  • Begin receiving girders onsite
  • Continue maintenance of traffic control devises.

I-91 SOUTHBOUND ROLLING ROADBLOCKS NOTIFICATION:

Beginning October 24, 2019, weather permitting at 7:00 a.m. and 12:30 p.m.  starting at Exit 7, motorists can expect a rolling roadblock for approximately a 30-minute delay to allow for beam deliveries. These deliveries will be Monday through Friday.

NARROW LANES – REDUCED SPEEDS – USE CAUTION!

The anticipated work schedule on VT 117 for October 10, 2019

Written by on October 9, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • Weather permitting, continue pavement markings
  • Continue sign installation
  • Continue mailbox adjustments
  • General cleanup work

PLEASE SLOW DOWN!  SAFETY FIRST!

The anticipated work schedule for October 9, 2019

Written by on October 8, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • Weather permitting, continue pavement markings
  • Continue sign installation
  • Continue mailbox adjustments
  • General cleanup work

PLEASE SLOW DOWN!  SAFETY FIRST!

The anticipated work schedule for October 8, 2019

Written by on October 7, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117
  • Weather permitting, continue driveway tie-ins.
  • Weather permitting, continue pavement markings
  • Continue sign installation

PLEASE SLOW DOWN!  SAFETY FIRST!

The following work schedule on VT 117 for the week beginning Saturday, October 5, 2019

Written by on October 3, 2019 in ESSEX, JERICHO-RICHMOND VT ROUTE 117

Saturday, Monday through Friday:

  • Weather permitting, continue pavement markings
  • Continue sign installation
  • Continue mailbox adjustments
  • General cleanup work

Monday:

  • Completion of shoulder work

Tuesday & Wednesday:

  • Weather permitting, completion of paving driveway tie-ins.

MOTORISTS SHOULD PLAN FOR DELAYS

Traffic control will be present allowing for one-lane of alternating travel within the construction zones.  The speed limit will be enforced!

PLEASE SLOW DOWN!  SAFETY FIRST!