VT 117 July 10, 2018:

– Cold planning will continue between VT-289 on ramp and Sand Hill Road.
– Continued underdrain and culvert work between Sand Hill Road and the Essex/Jericho town line.

Traffic control will be present allowing for one lane of alternating travel. Expect delays.

The anticipated work schedule for I-91 Rockingham Bridges:

Written by on July 6, 2018 in Rockingham Bridges-I91

For the week beginning Monday, July 09, 2018:

I-91 northbound bridge activities:

 Monday:

  • Dismantle one crane to relocate (this may go into Tuesday)

 Tuesday thru Friday:

  • Complete beam erection with daily rolling road blocks see below
  • Truck traffic on Golden Hill Road

  I-91 APPROX. ROLLING ROAD BLOCK SCHEDULES for beam deliveries:

  • Southbound: . 7:30am & 12:00pm for approx. 10 mins.
  • Northbound:   8:30am & 2:00pm for approx.. 20 mins.

NOTE:  If all beams are set by Thursday afternoon there will not be any rolling road blocks for Friday.

Please note rolling road block times could vary due to unforeseen circumstances.

*  The northbound rolling road blocks also includes the Exit 6 on ramp.  Motorists may want to detour on Route 5 to use the Exit 7 on ramp in Springfield to avoid delays.

The following is the anticipated work schedule for the VT 117 project:

The following is the anticipated work schedule for the week beginning Saturday,  July 07, 2018:

 Saturday thru Friday:

  • Continue installing underdrain from N. Williston Road to the intersection of VT 289.
  • Shoulder cleanup from VT 289 interchange to approx.. Tiffany Lane.

 Monday thru Friday:

  • Milling to begin from approx.. Tiffany Lane, Essex to Sand Hill Road with VT 289 interchange area gapped out. This work will grind down the existing roadway 4” – motorists should prepare for rough surface conditions.

Motorists should expect long delays and may want to seek alternate routes. 

VT Route 2 & 2A

There will not be any work on this project until further notice.

Friday, July 06, 2018:

Underdrain work to continue between Essex/Jericho Town line and Sand Hill Road.

The following is the anticipated work schedule for Bridge #8:

Written by on July 5, 2018 in BRIDGE 8 VT ROUTE 17

For the week beginning Monday, July 09, 2018. 

 Monday thru Sunday:

  •  Continue preparation for placement of concrete deck.
  • Continued work on the east roadway approaches to the bridge.
  • Placement of the concrete deck for the later part of the week.

The contractor is on schedule.

 

The anticipated work schedule for VT 116:

Written by on July 5, 2018 in Middlebury-Starksboro VT 116

The following is the anticipated work schedule for the week beginning Monday,  July 09, 2018: 

Monday thru Friday:

  • Continued sign installation between Bristol and Middlebury.
  • Continued culvert replacement between VT-125 intersection to Cady Road.  This culvert replacement will cause 1-way traffic controlled by a traffic signal with a 10’ wide lane restriction.

VT 117 Update:

No work tomorrow – Have a happy & safe July 4th celebration!

Thursday, July 5, 2018

  • Underdrain work resumes between the Essex/Jericho town line and Sand Hill Road.
    Motorists should expect delays!  Traffic control will be present!

Tuesday, July 3, 2018 until Noon:

The anticipated work schedule is as follows:
– Continued tree limb trimming between N. Williston Road and VT 289 intersection.
 
Motorists may choose to seek alternate routes as they can expect delays during peak hours. Traffic control will be present allowing for 1-lane of alternating traffic within the construction zones.

The following is the anticipated schedule for the I-91 Rockingham Bridges

Written by on June 29, 2018 in Rockingham Bridges-I91
The following is the anticipated schedule for the I-91 Rockingham Bridges

 

The schedule beginning Friday, June 29, 2018 thru Tuesday, July 3, 2018 @ noon:

I-91 northbound bridge activities:

  • Continued beam erection on Pier 1 and to Pier 2
  • Erect 16000lb crane to Abutment 1 – southbound
  • Truck traffic on Golden Hill Road

Work to resume on Monday, July 09, 2018.

I-91 APPROX. ROLLING ROAD BLOCK SCHEDULES for beam deliveries:
– Friday: Approx.. 5:00am southbound for approx. 10 mins. and approx. 6:30am northbound for approx. 20mins.
– Saturday: Approx. 2:30am & 4:00am southbound for approx. 10 mins. and approx. 3:15am & 7:30am northbound for approx. 20mins.
– Sunday: Approx.. 5:00am southbound for approx. 10 mins. and approx. 6:30am northbound for approx. 20mins.
– Monday: Approx. 2:30am & 4:00am southbound for approx. 10 mins. and approx. 3:15am & 7:30am northbound for approx. 20mins.
– Tuesday: Approx.. 5:00am southbound for approx. 10 mins. and approx. 6:30am northbound for approx. 20mins.

Please note rolling road block times could vary due to unforeseen circumstances.
* The northbound rolling road blocks also includes the Exit 6 on ramp. Motorists may want to detour on Route 5 to use the Exit 7 on ramp in Springfield to avoid delays.