The following is the anticipated work schedule for the VT 116 project:

Written by on June 21, 2018 in Middlebury-Starksboro VT 116

For the week beginning Monday, June 25, 2018:

Monday thru Friday:

  • Continued shoulder cleanup between Notch Road, Bristol & Quarry Road, E. Middlebury.
  • Begin shoulder widening between VT 125 & Airport Road for storm water pipe crossing.

1st beam to northbound abutment

Written by on June 21, 2018 in Rockingham Bridges-I91, Uncategorized
1st beam to northbound abutment

The following in the anticipated schedule for the I-91 Rockingham Bridges

Written by on June 15, 2018 in Rockingham Bridges-I91

For the week beginning, June 18, 2018:

I-91 northbound bridge activities:

 Monday thru Friday – Daytime:

 I-91 ROLLING ROAD BLOCKS  to allow for beam deliveries:

At approx.. 8:00am and 11:00am southbound for approximately 30 minutes

At approx.. 10:00am and 2:00pm northbound* for approximately 30 minutes

Please note rolling road block times could vary due to unforeseen circumstances.

* The northbound rolling road blocks also include the Exit 6 on ramp.  Motorists may want to follow the detour on Route 5 to use the Exit 7 on ramp in Springfield to avoid delays.  Oversize trucks must follow their permitted route. 

  • Continued beam erection
  • Complete removing forms from Abutment 1
  • Cleanup of Abutment 1 and begin backfilling
  • Truck traffic on Golden Hill Road

 

 

The following is the anticipated schedule for VT Route 2A & US 2 project:

Currently, there isn’t any work scheduled for this project until July 2, 2018.

The following is the anticipated work schedule for the VT 116 project:

Written by on June 14, 2018 in Middlebury-Starksboro VT 116

The anticipated work schedule for the week beginning Monday,  June 18, 2018:

 Monday thru Friday:

  • Continued ditch work. Between East Middlebury and Bristol
  • Sign installation from the “Lord’s Prayer Rock” to Starksboro

Traffic control will be present allowing for one lane of alternating traffic within the construction packages.

The following is the anticipated work schedule for Bridge #8 on VT 17

Written by on June 14, 2018 in BRIDGE 8 VT ROUTE 17
The following is the anticipated work schedule for Bridge #8 on VT 17

BRIDGE #8 ON VT ROUTE 17 REMAINS CLOSED TO TRAFFIC.

ALL motorists to follow the signed detour.

For the week beginning Monday, June 18, 2018:

Monday thru Sunday:

  • Structural steel to be set in place as the new precast abutments have been set.

Steel to be placed

East abutment

 

 

The following is the anticipated schedule on the I-91 Rockingham Bridges:

Written by on June 8, 2018 in Rockingham Bridges-I91
The following is the anticipated schedule on the I-91 Rockingham Bridges:

For the week beginning Monday, June 11, 2018:

I-91 northbound bridge activities:

Daily I-91 ROLLING ROAD BLOCKS  to allow for beam deliveries:

At approx.. 8:00am and 11:00am southbound for approximately 30 minutes

At approx.. 10:00am and 2:00pm northbound* for approximately 30 minutes

Please note rolling road block times could vary due to unforeseen circumstances.

*  The northbound rolling road blocks also includes the Exit 6 on ramp.  Motorists may want to detour on Route 5 to use the Exit 7 on ramp in Springfield to avoid delays.

  • Continued beam erection
  • Complete Abutment 1 support walls and remove forms
  • Truck traffic on Golden Hill Road

 

The following is the anticipated schedule for Bridge #8 on VT Route 17:

Written by on June 8, 2018 in BRIDGE 8 VT ROUTE 17

BRIDGE #8 ON VT ROUTE 17 IS CLOSED TO TRAFFIC.

ALL motorists to follow the signed detour.

 

The following is the anticipated work schedule for the week beginning Monday, June 11, 2018. 

It is anticipated the contractor will be working 7 days/week to get this project completed.

Monday thru Sunday:

  • Work continues on the removal of the existing bridge.

The following is the anticipated schedule for VT Route 116:

Written by on June 7, 2018 in Middlebury-Starksboro VT 116

The following is the anticipated work schedule for the week beginning Monday, June 11, 2018:

All work this week will be between East Middlebury/Middlebury to Bristol on VT 116

Monday thru Friday:

  • Continued ditch work.

 Motorists should expect delays as traffic control will be present allowing for one lane of alternating traffic within the construction areas.

The following is the anticipated schedule for VT Route 2A & US 2 project:

The following is the anticipated schedule on Route 2 for the week beginning Monday, June 11, 2018:

Monday thru Friday: Daytime – 6:30am to 7:00pm

  • Drainage work between the Harvest Lane/Blair Park and North Brownell Roads intersections in the westbound lane.

 

Motorist be aware that we are going to try to maintain 2-way traffic at all times however use caution while traveling thru the construction areas.