The anticipated schedule for the week beginning Monday, May 21, 2018:

All work this week will be between East Middlebury/Middlebury to Bristol on VT 116

 Monday thru Wednesday:

  • Weather permitting, continued paving.

 Monday thru Friday:

  • Various operations to include guardrail replacement and ditch work.

 Motorists should expect delays as traffic control will be present allowing for one lane of alternating traffic within the construction areas.

The anticipated schedule for the week beginning Monday, May 21, 2018:

Written by on May 17, 2018 in BRIDGE 8 VT ROUTE 17

Monday thru Friday:

  • Continued driving steel H piling that will be utilized to support the new structure while preparing for demolition of the existing bridge.

 Motorists should expect traffic control to be present allowing for one lane of alternating traffic.

  June 4, 2018 remains the anticipated closure date of the bridge.  Signs to be installed this week but will remain covered until the detour begins.   

The following is the anticipated schedule on Route 2 for the week beginning Monday, May 14, 2018:

Monday thru Friday: Daytime – 6:30am to 7:00pm

  • Work continues on the installation of the traffic signals at both the Harvest Lane/Blair Park and North Brownell Roads intersections.

Tuesday thru Thursday: Nighttime – 7:00pm to 6:00am

  • New traffic signal installation at the Brownell Roads intersection.

 

The following is the anticipated work schedule for the week beginning Monday, May 14, 2018:

Written by on May 10, 2018 in Middlebury-Starksboro VT 116

Monday thru Friday:

  • Weather permitting, paving begins on VT 116 from the southern end Route 7 intersection proceeding north to Bristol.

 Motorists should expect delays as traffic control will be present allowing for one lane of alternating traffic within the construction areas.

The following is the anticipated schedule for Monday, May 14, 2018:

Written by on May 10, 2018 in BRIDGE 8 VT ROUTE 17

Monday thru Friday:

  •  Prep work begins for the June 4, 2018 anticipated closure of the bridge with a well signed detour planned.

 Motorists should expect traffic control to be present allowing for one lane of alternating traffic.

Update for week beginning Monday, May 5, 2018

• Weather permitting, work continues on the installation of the traffic signal pole foundation at North Brownell Road.

• New traffic signal installation at the Blair Park/Harvest Lane intersection.

The hours of operation will be from 6:30am until 7:00pm. It is anticipated to keep 2-way traffic flowing during peak hours. If necessary, traffic control will be present to allow for 1-lane of alternating traffic during 9:00am until 2:30pm.

Middlebury-Starksboro VT 116

Middlebury-Starksboro VT 116

 The following is the anticipated work schedule for the week beginning Monday, May 07, 2018:

All work this week will be between East Middlebury/Middlebury to Bristol

  • Widening shoulders continues north to Quarry Road both northbound and southbound on VT 116
  • Milling continues
  • Ditch work continues

Motorists should expect delays as traffic control will be present allowing for one-way alternating traffic within the areas of construction activities.

 

 

BRIDGE 8 – VT ROUTE 17 NEW HAVEN, VT

Written by on October 6, 2017 in BRIDGE 8 VT ROUTE 17, Current Road Work
BRIDGE 8 – VT ROUTE 17  NEW HAVEN, VT

PUT YOUR CELL PHONE DOWN!

IT IS AGAINST THE LAW TO USE HAND HELD DEVICES WHILE DRIVING. IF CAUGHT, YOU WILL BE FINED, AND 4 POINTS GO ON YOUR LICENSE!

BRIDGE 8 VT ROUTE 17 Fact Sheet

Written by on October 1, 2017 in Uncategorized
BRIDGE 8 VT ROUTE 17 Fact Sheet

Route 11/Chester Road Culvert Project

Written by on August 11, 2017 in ZArchives
Route 11/Chester Road Culvert Project

Springfield location pic

The Vermont Agency of Transportation (VTrans) in conjunction with Cold River Bridges will be installing a temporary bridge on VT Route 11 at Bridge #57 just east of Breezy Hill Road and/or 1.3 miles west of the VT 106 & River Street intersection.  This bridge will be installed with a northern shift in the roadway thus taking traffic off the sinking eastbound travel lane.  The installation of the temporary bridge should be completed by September 1, 2017.

This VTrans project installing a temporary bridge on VT Route 11 at Bridge #57 just east of Breezy Hill Road and/or 1.3 miles west of the VT 106 & River Street intersection is complete.

 We realize that we didn’t meet the targeted completion date of September 1, 2017 so on behalf of VTrans and myself, we would like to thank you all for your patience and understanding during this install of the temporary bridge.

VTrans is actively working on the engineering and design for the culvert replacement.  A date is not set for construction however before any construction begins notifications will be sent out.    

Thank you.