The anticipated schedule for the week beginning Monday, May 21, 2018:

Written by on May 17, 2018 in BRIDGE 8 VT ROUTE 17

Monday thru Friday:

  • Continued driving steel H piling that will be utilized to support the new structure while preparing for demolition of the existing bridge.

 Motorists should expect traffic control to be present allowing for one lane of alternating traffic.

  June 4, 2018 remains the anticipated closure date of the bridge.  Signs to be installed this week but will remain covered until the detour begins.   

The following is the anticipated schedule on Route 2 for the week beginning Monday, May 14, 2018:

Monday thru Friday: Daytime – 6:30am to 7:00pm

  • Work continues on the installation of the traffic signals at both the Harvest Lane/Blair Park and North Brownell Roads intersections.

Tuesday thru Thursday: Nighttime – 7:00pm to 6:00am

  • New traffic signal installation at the Brownell Roads intersection.

 

The following is the anticipated work schedule for the week beginning Monday, May 14, 2018:

Written by on May 10, 2018 in Middlebury-Starksboro VT 116

Monday thru Friday:

  • Weather permitting, paving begins on VT 116 from the southern end Route 7 intersection proceeding north to Bristol.

 Motorists should expect delays as traffic control will be present allowing for one lane of alternating traffic within the construction areas.

The following is the anticipated schedule for Monday, May 14, 2018:

Written by on May 10, 2018 in BRIDGE 8 VT ROUTE 17

Monday thru Friday:

  •  Prep work begins for the June 4, 2018 anticipated closure of the bridge with a well signed detour planned.

 Motorists should expect traffic control to be present allowing for one lane of alternating traffic.

Update for week beginning Monday, May 5, 2018

• Weather permitting, work continues on the installation of the traffic signal pole foundation at North Brownell Road.

• New traffic signal installation at the Blair Park/Harvest Lane intersection.

The hours of operation will be from 6:30am until 7:00pm. It is anticipated to keep 2-way traffic flowing during peak hours. If necessary, traffic control will be present to allow for 1-lane of alternating traffic during 9:00am until 2:30pm.